Hannas
Shaping Tomorrow with You
Our History
Our People
Our Capabilities
Chairman's Statement
Clients and Partners
Eastern Pipeline Alliance
Shell Refinery (Aust) Pty Limited
Announcements
Earthworks
Department of Defence Headquarters Project
Stabilisation and Retaining Wall Construction
Roads
Roadworks and Office Complex
Water
Pump Stations and Storage Tanks Civil Works
Rail
Hornsby Platform 5 and Stabilising Works
Heavy Industry
Crude and Diesel Tank Project
Shell MOGAS Project
Structures
Substation Building and Civil Works
Property Investment
Property Development
Residential Apartment Development, Penrith, NSW
Our Services
Facilities Management - Alliance Relationship
Company Policies
Safety
Caltex Clean Fuels Project
Environment
Land Remediation and Reclamation
Community
Kyle Bay Foreshore Restoration
Tender Opportunities
Terms & Conditions
EOI
Contact Us
Positions Avaliable
Career Programs
Civil & Construction
>
Heavy Industry
>
Crude and Diesel Tank Project
Case Study
Crude and Diesel Tank Project
Client
: Uhde Shedden / Caltex Australia
Location
: Caltex Oil Refinery - Kurnell, NSW
Project Type
: Heavy Industry - Crude and Diesel Tank Project
Duration
: 15 months
Scope of Work
:
Caltex financed the construction of 18ML diesel tank and 88ML crude oil tank aimed to meet the increased demand of diesel on the current market.
Hannas Civil Engineering Pty Ltd was awarded the contract for carrying out all the related civil works as part of the 50 Million AUS$ overall project.
Civil works carried out by Hannas include construction of ring beam foundations for the tanks, retaining walls, containment bunds, drainage systems, installation of HDPE liner to foundations and tank farms, protective shotcreting works to bund walls, installation of oily water sewer system, roads construction, installation of electrical conduits and civil support to various works directly carried out by the Client.
These works were carried out under very strict safety and environmental regulations, whilst work interfaces with the tanks constructors’ required continuous negotiation and works coordination.
Following the award of the initial 3M AUS$ stage 1 civil works package, Hannas were awarded the additional 2M AUS$ stage 2 works for the diesel tank project. This was a consequence of the quality of the works delivered during stage 1 as well as Hannas’ continuous attention in interpreting and meeting Client’s expectations.
Project Contact
: Joel Hewitt